SMITH ROAD AND CONNIE LANE IMPROVEMENT PROJECT

Aerial map showing the location of construction at Smith Road and Connie Lane next to FM 550.

The Smith Road and Connie Lane Improvement Project is scheduled to begin on Wednesday, March 16, 2026, with an anticipated completion date of May 18, 2026, weather permitting.

The project will begin with Connie Lane, covering approximately 4,000 linear feet, followed by Smith Road, covering approximately 6,000 linear feet. The scope of work includes asphalt road reclamation and the installation of a 3-inch asphalt overlay to improve ride quality and extend the service life of the pavement.

To ensure the safety of workers and motorists, the roadways will be limited to one-way traffic, with the opposite direction fully closed during active construction phases. Traffic control signage and personnel will be in place throughout the duration of the project.

Driveway access will be maintained for residents, and trash and recycling services will continue as normal during construction.

The City appreciates the community’s patience as these important roadway improvements are completed. Once finished, the upgraded asphalt surface will enhance safety, improve drivability, and preserve the integrity of these neighborhood roadways for years to come.